Indicators Using Earned Value
Schedule Variance (SV)
This is how far off schedule your project has slipped. It
is the difference between the work actually performed
and the work that was scheduled to have been performed,
i.e. the difference between BCWS and BCWP.
Mathematically, Schedule Variance is:
SV = BCWP(cum to date) – BCWS(cum to date)
A negative value indicates that the project is behind
schedule, a positive value that it is ahead of schedule.
Cost Variance (CV)
This value represents how close to budget your project is.
It is the difference between the actual cost of the work
performed and the value of the work performed.
Mathematically, Cost Variance is:
CV = BCWP(cum to date)– ACWP(cum to date)
A negative value means you have over-spent, while a
positive value means you have under-spent.
Budget at Complete (BAC)
This is the total BCWS for the activity, cost bin, or
project. It represents the total budgeted cost of
completing that item, for example the total cost of an
activity across all cost bins.
Mathematically, Budget at Complete is:
BAC = BCWS(total)
Estimate at Complete (EAC)
This is the projected actual cost for the activity, cost bin,
or project. Effectively, it uses the ACWP to date and the
estimate for the remaining work to provide an estimate of
what the total ACWP will be at the end of the item.