Ecowatt schedule and the Spring 2007 Semester Schedule, the team derived a preliminary schedule for next semester, represented with a Gantt Chart (Figure 5 - Gantt Chart of Spring Semester Plan). Towards the end of the Spring 2008 Semester, Ecowatt met to again to analyze the team’s adherence to the predetermined schedule, which was not as close to the plan as the team had hoped. Output regulation redesigns postponed the ordering of parts until later in the semester, and the Biobattery construction (membrane and electrode assemblies especially) proved more tedious and time-consuming than anticipated. Cost-effective gold wire was also particularly difficult to acquire. All in all, the team met the course established deadlines as well as many of the additional deadlines set up at the end of the Fall 2007 semester – being constantly driven by an ambitious planned Gantt Chart. 22