Feed-in Tariff: Central FIT Register User Guide
08 March 2013
Licenced Electricity Suppliers
When selecting the tick box for
previous installations you are required to
provide details of the TIC and DNC.
Select the correct Technology
Type from the drop down list.
3.44. Please note that „Hydro‟ does not go through the MCS process in the CFR, if
you have a Hydro application the Generator will need to apply through the ROOFIT process.
3.45. To ensure the allocation of the correct tariff code for a photovoltaic
installation, the PV installation type must also be defined. Where the TIC of the
installation is 4kW or less there are three options:
Retrofit
New build
Standalone
3.46. For PV installations with a TIC greater than 4kW to 50kW there are two
options:
Standard
Standalone