Download Charges and Incentives User Guide
Transcript
Charges and Incentives User Guide What is the cost wash-up? The cost wash-up reconciles the difference in the pence per kWh tariffs charged in each period, and the actual pence per kWh tariffs which Network Rail paid for that electricity, and results in a payment to or from the train operator to Network Rail. Both metered and modelled train operators participate in the cost wash-up. What is the difference between the AC and DC network? The AC (alternating current) network uses overhead lines to power trains. The DC (direct current) network uses a third rail to power electric trains. The majority of the Sussex, Wessex and Kent use the third rail (DC) to power their train services. There are considerably higher transmission losses on the DC network, owing to the lower voltage. Rail Delivery Group 12