Download Charges and Incentives User Guide

Transcript
Charges and Incentives User Guide
What is the cost wash-up?
The cost wash-up reconciles the difference in the pence per kWh tariffs charged in each
period, and the actual pence per kWh tariffs which Network Rail paid for that electricity, and
results in a payment to or from the train operator to Network Rail.
Both metered and modelled train operators participate in the cost wash-up.
What is the difference between the AC and DC network?
The AC (alternating current) network uses overhead lines to power trains. The DC (direct
current) network uses a third rail to power electric trains. The majority of the Sussex, Wessex
and Kent use the third rail (DC) to power their train services. There are considerably higher
transmission losses on the DC network, owing to the lower voltage.
Rail Delivery Group
12