Cross-Lock system concealed demountable
INSTALLATION MANUAL
1. Determine the position of the suspensions. Suspension distances and distances
between secondary profiles are related to panel lay-out, dimensions and weight.
See our technical literature. In case of non standard situations ask for advice.
2. Mount suspension points and suspenders. Install primary beams in the correct
height. The perforations needed for Cross-Lock bracket fixation have to be inline
(detail B).
3. For fixation of the primary beam position and stability of the system primairy
beams have to be mounted to the wall using corner brackets (detail C).
Detail A
Detail C
1st suspension
max 450mm from
ceiling edge
1e primary profile
max 300mm from
ceiling edge
C
A
B
P = n x 300, max 1500
P
x
n
Detail B
V3, 03 / 2013
Saint-Gobain API BV
P.O. Box 1, 3840 Harderwijk, Netherlands
www.api.nl
G:\Product management\ProductOntwikkeling O-1\_Diversen\API Documentatie\_Montage en training instructies\2 Cross-Lock systemen\VER 3, 29-03-2013\
3