Download INSTALLATION MANUAL
Transcript
Cross-Lock system concealed demountable INSTALLATION MANUAL 1. Determine the position of the suspensions. Suspension distances and distances between secondary profiles are related to panel lay-out, dimensions and weight. See our technical literature. In case of non standard situations ask for advice. 2. Mount suspension points and suspenders. Install primary beams in the correct height. The perforations needed for Cross-Lock bracket fixation have to be inline (detail B). 3. For fixation of the primary beam position and stability of the system primairy beams have to be mounted to the wall using corner brackets (detail C). Detail A Detail C 1st suspension max 450mm from ceiling edge 1e primary profile max 300mm from ceiling edge C A B P = n x 300, max 1500 P x n Detail B V3, 03 / 2013 Saint-Gobain API BV P.O. Box 1, 3840 Harderwijk, Netherlands www.api.nl G:\Product management\ProductOntwikkeling O-1\_Diversen\API Documentatie\_Montage en training instructies\2 Cross-Lock systemen\VER 3, 29-03-2013\ 3