STP 9-94K13-SM-TG Perform Test System Alignment (AHCAL)
093-94K-1112
Conditions: Perform this task in a contemporary operational environment given a 94K, an EETF, a
generator set or commercial power, TM 11-6625-3085-12-1, TB 11-6625-2773-35, and
TB 11-6625-3085-50.
Standards: The EETF is aligned within the time required by the AHCAL software.
Performance Steps
1. Ensure power up to full power has been accomplished in accordance with TM 11-6625-3085-12-1,
paragraph 2-3-74.
2. Follow procedures in accordance with TB 11-6625-3085-50, paragraph 4-1, or as directed by
NCOIC.
3. Execute the alignment module as directed by NCOIC.
4. Repeat step 3 for each module requiring alignment.
5. Perform back-up procedures in accordance with TB 11-6625-3085-50, paragraph 4-9-d.
6. Observe all safety precautions.
Performance Measures
GO
NO-GO
1. Ensured power up to full power was accomplished in accordance with
TM 11-6625-3085-12-1, paragraph 2-3-74.
——
——
2. Followed procedures in accordance with TB 11-6625-3085-50, paragraph 4-1 or
as directed by NCOIC.
——
——
3. Executed the alignment module as directed by NCOIC.
——
——
4. Repeated step 3 for each module requiring alignment.
——
——
5. Performed back-up procedures in accordance with TB 11-6625-3085-50,
paragraph 4-9-d.
——
——
6. Observed all safety precautions.
——
——
Evaluation Guidance: Score the Soldier GO if all performance measures are passed (P). Score the
Soldier NO-GO if any performance measure is failed (F). If the Soldier fails any performance measure,
show what was done wrong and how to do it correctly.
References
Required
DA PAM 750-8
TB 11-6625-3085-50
TM 11-6625-3085-12-1
7 December 2007