Preventive maintenance is defined as a planned strategy of cost-effective treatments applied
to an existing roadway system that preserves the system, retards future deterioration, and
maintains and improves the functional condition of the system (without substantially increasing
structural capacity) (1). Although many agencies have implemented preventive maintenance
programs, there is still very little available guidance on determining the optimal timing of such
treatments. The analysis tool developed for this project is intended to bridge that gap by
implementing a methodology for calculating optimal timing. Although the analysis tool does not
use a true optimization strategy (i.e., all possible treatment application times are not analyzed), it
does provide a simple method for choosing the most effective treatment timing from a set of
performance and cost data reflecting the application of a preventive maintenance treatment
applied at different pavement ages.
This User’s Guide is a hands-on introduction to using the macro-driven Microsoft® Excelbased analysis tool (OPTime) that was developed under National Cooperative Highway Research
Program (NCHRP) project 14-14, “Guide for Optimal Timing of Pavement Preventive
Maintenance Treatment Applications.” It is not intended to answer all questions about the
underlying analysis approach, as the analysis approach is described in much greater detail in
chapter 3 of the main report. However, it does provide detailed information organized into the
following five areas:
ƒ
Analysis tool capabilities—This section describes the capabilities and intended use of the
OPTime analysis tool.
ƒ
Key concepts of the methodology—For quick reference, this section summarizes many of
the important terms that are encountered during the setup and conduct of an analysis
session.