However, all these suggestions are best attempted in consultation with all the stakeholders in the plasterboard
capture system. The next section provides some guidance on how to undertake this process.
7.3
Planning a plasterboard capture system
For capture systems to function effectively, it is important to ensure stakeholder buy-in early on in the project.
Early implementation is preferential to trying to implement a capture system mid-way through a programme.
By planning the operation of a capture system upfront in the programme and involving all the relevant
stakeholders, it is not necessary to stimulate change in the site practices later on. It also allows for the planning
and erection of chutes and other auxiliary items.
The stakeholders involved in a plasterboard capture system are:
„
„
„
main contractor;
dry lining sub-contractor; and
waste management company/plasterboard recycling company.
If a project is dealing directly with a plasterboard manufacturer or indirectly through a distributor, it is
advantageous to also engage with these parties.
To stimulate change on site, there needs to be a strong, proven business case in order to ensure buy-in. Different
levels of management require different levels of business case (Table 20), both in terms of incentives and also in
terms of methodology.
Table 20 Requirements to promote buy-in to the proposed plasterboard capture system
Management level
Level of business case
Site management
High level figures.
Proven case studies.
Demonstration of machine.
Involve in establishing methodology on site.
Ensure buy-in before approaching labourers.
Use foreman to dictate change.
Demonstrate usage on site.
Site foreman
Site labourers
As noted above, there is often a need to highlight the misconceptions regarding existing systems. This could
include:
„
„
„
ensuring that the true cost of waste is understood;
highlighting inefficiencies with current methods of plasterboard capture; and
ensuring clear and delegated responsibilities.
Once all parties are engaged, it is preferable to hold a meeting with everyone present in order to work through a
logical progression of the dry lining process on site. This meeting should seek to:
„
identify any inefficiency with the proposed method of works – materials lying around on site for a time,
double-handling of the waste, excess waste budgeted for in the take- off (If it is 10%, why is it 10%?); and
„
work together to propose more sustainable solutions.
Capture of waste plasterboard on construction sites 49