2.1.4 Implementation
This is the phase when the system is actually built. The sub-phases of
this phase are:
2.1.4.1 Construction
It is the phase when all the parts of the system are developed.
Programming or coding is often seen as the focal point in this phase [2].
2.1.4.2 Testing
Testing is basically done along with the coding and the codes are
edited as the programs are written and tested. Tests are done in different
stages such as unit testing is done when each module is completed and they
are tested independent of each other. When it succeeds unit testing the
modules are integrated and an integration test is done to examine if the
modules as a whole works fine. After successful integration testing system
test is carried out to examine whether the system (the hardware, the software
and the network infrastructure) as a whole performs well [1].
2.1.4.3 Conversion
This is the conversion process by which the new system replaces the
old. There are different types of conversion methodologies e.g. direct
conversion (the new system immediately replaces the old system), parallel
conversion (both the old and new systems are operated for a month or two
until it is clear that there are no bugs in the system), phased conversion (the
system or a part of the system is installed in one part of the organization as an
initial trial and then gradually installed in others) etc [2].
2.1.4.4 Training
Since the old system is replaced or radically changed by the new
system the users need to be trained. In this phase the development team
along with the committee decides whom to train, what to train and how to train