SITE OPERATIONS PLAN
Objective
The Site Operations Plan (SOP) is an executive document for planning, specific for each team, in which they
must take into account all of the activities, resources, needs and deadlines. The Plan has to guarantee the
assembly and disassembly of the house with logic, order and total safety. Every team must hand in its Plan to
the organization, who will draw up the general Site Operations Plan of the Solar Village that will harmonize the
needs of all teams and avoid interference. The organization will revise all of the Site Operations Plans of the
teams to verify their efficiency and identify possible conflicts between them.
The organization will develop a general Site Operations Plan of the Solar Village; based on the information sent
by the teams in their Site Operations Plan. This is why it is very important for the plans to be as specific as
possible.
Content & Structure
The Site Operations Plan will be required from Deliverable #3 onwards and will have to comply with all the
requirements specified in Rule 4 – Solar Village. Information will be updated and specified along with the project
development, including further details in each deliverable. The plan consists of the Site Operations drawings (to
be included in the Project Drawings), the Site Operations Report (to be included in the Project Manual). The Site
Operations report must, at least, include the following sections:
1. Precedents and aim
2. General Data
3. Site Operations Team Coordinator
4. Outside Logistic. Solar Village
I. Phases description
II. Transport
III. Vehicles/Transports circulation
5. Inside Logistic. Approximation
I. Phases description
II. Deciding factors
III. Infrastructures
IV. Waste management
6. Load / Unload
7. Assembly / Disassembly
8. Timeline. Trucks and machinery needed entrance times, order, unload, interval between vehicles and
assembly times associated.
9. Site Operations Chart (Teams must fill in this file, available in the SDE WORKSPACE).
10. Assembly & Disassembly Chart (Teams must fill in this file, available in the SDE WORKSPACE).
HEALTH & SAFETY REPORT & SPECIFIC TERMS AND CONDITIONS DOCUMENT
The Health & Safety Report, as well as the Health & Safety Specific Terms and Conditions Document, are part of
the HS Plan of the project. Please refer to Section 4.0, Rule 52 for further details.
DETAILED WATER BUDGET
The water budget information may either be split between the Project Drawings and this section of the Project
Manual, or provided entirely in the Project Drawings. If the information is split, make sure this section of the
Project Manual is clearly referenced on the relevant drawing sheet(s).