Commissioning
6.1 Safety guidelines for commissioning
Note
Voltage Protection Module VPM
Above a speed, defined for each motor, each motor requires a Voltage Protection Module
VPM. Refer to the Configuration Manual "Naturally cooled SIMOTICS T-1FW6 built-in torque
motors" on this topic.
Notes for checking the insulation resistance
WARNING
Risk of electric shock
If, at a plant/machine equipped with direct drives or directly at the motors you check the
insulation resistance using high-voltage, this can damage the motor insulation! Examples
necessitating that the insulation resistance is checked include the installation test,
preventive maintenance and troubleshooting.
• Only use test equipment that is in compliance with DIN EN 61557-1, DIN EN 61557-2
and DIN EN 61010-1 or the corresponding IEC standards.
• The test may only be carried out with a maximum direct voltage of 1000 V for a
maximum time of 60 s!
• Measure the test voltage with respect to ground or the motor enclosure.
• If a higher DC or AC voltage is necessary to test the machine/plant, you must coordinate
the test with your local Siemens office!
• Carefully observe the operating instructions of the test equipment!
Always proceed as follows when testing the insulation resistance of individual motors:
1. Connect all winding and temperature sensor connectors with each other; inspection
voltage not to exceed 1000 VDC, 60 s against PE connection.
2. Connect all temperature sensor connectors to the PE connector and all winding
connectors with each other; the inspection voltage must not exceed 1000 VDC, 60 s,
winding against PE connector.
Each insulation resistance must be at least 10 MΩ, otherwise the motor insulation is
defective.