Brief instructions on commissioning ET 200S
2.1 Commissioning on PROFIBUS DP
2.1.2
Install the ET 200S
Proceed as follows
1. Install the DIN rail (35 x 7.5 mm or 15 mm) with a length of at least 210 mm on a solid
surface.
2. Mount the various modules onto the rail, starting on the left side (hang in - swivel down slide to left.) Follow the following sequence:
– Interface module IM151-1 STANDARD
– TM-P15N23-A1 terminal module
– 4 x TM-E15N24-A1 terminal module
– TM-P15N23-A1 terminal module
– 4 x TM-E15N24-A1 terminal module
– Terminating module
3. Set PROFIBUS address 3 on the IM 151-1 STANDARD interface module.
2)) 21
Figure 2-2
*
Setting PROFIBUS address 3
Intended for use with future add ins. Switch must be in OFF position.