w Vacuum holding test Hold the system at a pressure of –755mmHg or lower for 1 hour or longer, and confirm that the vacuum reading does not rise on the vacuum gauge. If it rises, moisture or leakage may exist in the system. However, take care not to leak air from the gauge manifold. If air enters, it is recommended to use the cupper tube directly instead of gauge manifold. e Charging of refrigerant After the vacuum-holding test, make the circuit vacuous again for approx. 10 minutes. Then, charge the specified amount of refrigerant through the service port on the liquid line using the charging cylinder. qVacuum-dehydrating (first time) ..... 2 hours wVacuum-breaking (first time) Nitrogen gas is pressurized to 0.5kg/cm2 from the service port on suction pipe. Since nitrogen gas breaks the vacuum, the effect of the vacuum-dehydrating is enhanced. However, if there is much moisture, it can not be removed by this method. Therefore, do not allow water entry or produce water during the refrigerant piping work. eVacuum-dehydrating (second time) Run the vacuum pump one hour or longer. (The achievable vacuum must be –755mmHg or lower.) If pressure of –755mmHg or lower can not be achieved even after vacuuming of 2 hours, repeat step wvacuum-breaking and evacuum-dehydrating. rVacuum holding test ..... 1 hour Same as normal vacuumtAdditional charge of refrigerant dehydrating Time chart of normal vacuum-dehydrating +0.5kg/cm2 Positive pressure Atmospheric pressure 0kg/cm2 Note: Make sure to use nitrogen gas for vacuum-breaking. (If any oxygen gas is used, it may explode.) –200mmHg Vaccume –400mmHg –600mmHg –700mmHg –760mmHg Time chart of special vacuum-dehydrating –755mmHg +0.5kg/cm2 Addtional pressure Vacuum-dehydrating Vaccum leaving test Charge of refrigerant Atmospheric pressure 0kg/cm2 (2 hours) (1 hours) Totally 3 hours –200mmHg [Special vacuum-dehydrating] This method is that the vacuum-breaking process with nitrogen gas is integrated one time or more in the same way as the normal vacuum-dehydrating process. Vacuum –400mmHg –755 mmHg Vacuum-holding test 1 hour Charge of refrigerant –755 mmHg Vacuum-dehydrating 2 hours –700mmHg –760mmHg Vacuum-breaking Vacuum-dehydrating 1 hour –600mmHg Totally 4 hours (1mmHg=0.0013kg/cm2=0.133Kpa) 4-23