Report. No.: GZ12100571-1R3
IEC / EN 60335-2-40
Clause
15.3
15.2
Requirement – Test
Result
(IEC) Drain pan filled to brim and subjected to
continuous overflow and fan(s) switched on
(EN)
(IEC/EN 60335-2-40)
15.101 (IEC) Spillage test as specified
(IEC 60335-2-40/A2)
Verdict
P
The appliance must be
installed on the height of 2,5m
or more above floor.
N/A
16
LEAKAGE CURRENT AND ELECTRIC STRENGTH
16.1
Leakage current not excessive and electric
strength adequate
P
Protective impedance disconnected from live
parts before carrying out the tests
P
Single-phase appliances: test voltage 1.06 times 1,06x240=254,4 V
rated voltage .............................................................:
P
16.2
Three-phase appliances: test voltage 1.06 times
rated voltage divided by √3.......................................:
16.3
N/A
Leakage current measurements
(see appended table)
P
Electric strength tests according to table 7
(see appended table)
P
No breakdown during the tests
17
18
——
P
OVERLOAD PROTECTION OF TRANSFORMERS AND ASSOCIATED
CIRCUITS
——
No excessive temperatures in transformer or
associated circuits in event of short-circuits likely
to occur in normal use
N/A
(see appended table)
Appliance supplied with 1.06 or 0.94 times rated
voltage and the most unfavourable short-circuit or
overload likely to occur in normal use applied .........:
N/A
Temperature rise of insulation of the conductors
of safety extra-low voltage circuits not exceeding
the relevant value specified in table 3 by more
than 15 K
N/A
Temperature of the winding not exceeding the
value specified in table 8,
N/A
however limits do not apply to fail-safe
transformers complying with sub-clause 15.5 of
IEC 61558-1
N/A
ENDURANCE
——
Not applicable (IEC/EN 60335-2-40)
N/A
TRF No.: IECEN60335_2_40B
Intertek Testing Services Shenzhen Ltd. Guangzhou Branch
Block E, No.7-2 Guang Dong Software Science Park, Caipin Road, Guangzhou Science City, GETDD, Guangzhou, China
Tel: (86-20) 8213 9688 Fax: (86-20) 32057538