Download D380 Installation and Operation Manual
Transcript
Installation Procedure Installing the Enphase Microinverter System involves several key steps: 1. Measuring service and Installing the AC branch circuit junction box 2. Attaching the Enphase Microinverters to the racking 3. Installing the AC interconnect cable and AC Trunk cables and connecting the Enphase Microinverters to the AC Trunk cables 4. Grounding the system 5. Connecting the PV Modules, and Completing the Enphase Installation map Each of the detailed installation steps in the following sections is numerically referenced in the installation diagram below. WARNING: DO NOT connect Enphase Microinverters to the utility grid or energize the AC circuit(s) until you have completed all of the installation procedures as described in the following sections. Page 10 Copyright Enphase Energy Inc. 2011 141-00009 Rev 10b