Andrew Turner – Automated Deployment Services Website
Appendix 2
Appendix 2.7 – Analysis of requested Infrastructure and
Laboratory Support (ILS) work process
The timings in Appendix 2.6 show the average amount of time measured for
steps in the requested work process shown in Appendix 2.5. Using these
values calculations can be made about deployment times using an Automated
Deployment Services (ADS) system.
Using an ADS system, a computer will take on average 20 minutes to deploy
an OS to a computer. As the ADS system uses multicast to deploy the OS the
time taken for X computer to be deployed is
Time for X computers = 20 minutes
As this formula does not contain X on the calculation die of the equation, the
time taken to deploy multiple computers is not larger than the time to deploy
one computer. This formula will work for up to 128 computers. More than 128
computers will result in two ‘Deploy OS image’ steps due to the 128 computer
limit on the multicasting.
Tables A2.7.1 and A2.7.2 show the amount of time taken for an ADS system
to deploy to one computer and five computers respectively
Time
Computer 1
0-
3-
6-
9-
12-
15-
18-
21-
= unattended
Table A2.7.1: Time taken to deploy one computer using ADS
Time
Computer 1
Computer 2
Computer 3
Computer 4
Computer 5
0-
3-
6-
9-
12-
15-
18-
21-
= unattended
Table A2.7.2: Time taken to deploy five computers using ADS
The maximum time taken for a computer to receive a new OS using an ADS
system can be calculated as
ADS(MAXIMUM TIME)
= 72 + 396 + 787 seconds
= 1255 seconds
= 21 minutes
The minimum time taken for a computer to receive a new OS using an ADS
system can be calculated as
ADS(MINIMUM TIME)
= 51 + 376 + 724
= 1151
= 19 minutes
- 72 -