End Use Meter Data Analysis
C.1
End Use Equipment Meter Data
C.1.1
Cooling Equipment
C.1.1.1
Split System Air Conditioner and Heat Pump
•
AC monitoring relies on data loggers recording average amperage every 20 minutes
using current transducers. The current draw data are combined with an instantaneous
power measurement (spot-watt) taken at the time of the meter installation.
•
It is then possible to translate these current readings into estimates of annual energy
consumption (kWh) of the air conditioner or heat pump.
•
Fan kWh is estimated by estimating the fraction of each period that the AC is running
and multiplying it by the kW input of the fan. To inform the run-time data with actual
power demand, a onetime spot power measurement of the condensing unit is taken
using a Fluke 31 power meter.
The air conditioner monitoring approach is to record total condenser run-time utilizing the OWL
400 data logger with a 0-2.5 vdc output 50 amp split core current transducer (CT). This
monitoring configuration operates by converting the analog signal of the 50 amp CT to a digital
signal usable by the OWL 400.
Energy consumption of blower fans for central cooling systems will not be metered explicitly, but
the fan is assumed to draw constant power during any condenser run period. The runtime for
air conditioning and heat pump systems will then multiplied by the fan power draw to determine
fan energy consumption. Cooling runtime for air conditioner and heat pump systems will
calculate using the data and equipment performance curves.
Cooling Runtime was calculated as follows:
1) First translate the measured amperage information into an estimate of runtime.
AMP = Average Amp data, 20-minute interval (OWL Data)
odb = condenser inlet dry bulb temperature (°F) (Hourly Data)