Step 2:
After the hydrogen (0.45-0.55 Bar) is supplied, the fan/blower should start to operate.
The hydrogen shall flow through the stack .The red light on the controller should be on for a short time and
then it will go off.
Connect a tube to the purging valve input.
Step 3: To obtain higher efficiency and better water management, please connect the other end of the
tube from the purging valve to the hydrogen outlet port.